How to file your solar system with LUMA in Puerto Rico

Expedited Registration · Act 17-2019 · checked in July 2026

The paperwork is what stops most systems, not the roof. This is the whole route in order: which path yours takes by size, the seven steps of the Expedited Registration, everything that has to go attached the first time, and what to do when LUMA does not answer.

Which path yours takes, by size

The size that counts is the inverter output in kW AC, not the panels on the roof. A 12 kW array behind a 7.6 kW inverter files as 7.6 kW.

SizePathWhat it means
Up to 25 kW AC Registro Expedito (GDL17)
Ley 17-2019
Online registration, no impact study. LUMA has 30 days to notify you.
Over 25 and up to 300 kW AC Interconnection evaluation
Reglamento 8915
Requires a technical evaluation by LUMA. The timelines run longer.
Over 300 kW AC Interconnection study
Reglamento 8915
Large system: a full study, with its own costs and timelines.

Size your system and get the kW AC →

Free, no card and no sign-up. The simulator tells you which path yours takes and works out the whole day hour by hour.

The seven steps of the Expedited Registration

This part comes with the Professional plan
Nobody has this written out in one place: it is spread across the Applicant Manual, Regulation 8915, Act 17-2019 and scattered LUMA bulletins.
Unlock with Pro
Sizing your system, hour by hour, stays free.

What has to go attached

File with all of it at once. A missing attachment does not pause the clock — it restarts it.

This part comes with the Professional plan
Nobody has this written out in one place: it is spread across the Applicant Manual, Regulation 8915, Act 17-2019 and scattered LUMA bulletins.
Unlock with Pro
Sizing your system, hour by hour, stays free.

If they do not answer, or reject it with no written reason

Most people just keep waiting because they do not know there is somewhere to go. There is.

This part comes with the Professional plan
Nobody has this written out in one place: it is spread across the Applicant Manual, Regulation 8915, Act 17-2019 and scattered LUMA bulletins.
Unlock with Pro
Sizing your system, hour by hour, stays free.

Where it gets filed

PREPAEE portal: https://prep-luma.lumapr.com/prepaGD/login/auth
Questions: nem@lumapr.com

Public information put in order, not legal advice. Sources: Expedited Registration Applicant Manual, Regulation 8915, Act 17-2019 and the Interconnection Agreement for 25 kW or less. Checked in July 2026 — the process changes, confirm on the portal before you file.